Where we heard itMorgan Stanley’s Thoughts on the Market podcast, “Solving AI’s Power Bottleneck,” Nov. 3, 2026. Dave Arcaro, the bank’s U.S. power, utilities and clean tech analyst, with autos analyst Andrew Percoco.
Morgan Stanley keeps raising its estimate of how much electricity America’s data centers will want and won’t be able to get. “The shortfall has grown in our estimates over the last several iterations,” utilities analyst Dave Arcaro said on the bank’s podcast on Nov. 3. Then he gave the new number.


Arcaro said the tightest point is often the wires. Utilities are “not used to growing this fast,” he said, and “it’s often their electric transmission network that is falling behind,” the long-distance lines and substation equipment that take years to build. “We expect them to fall short and pretty meaningfully short.” His colleague Andrew Percoco added that the bank’s teams see about 10 gigawatts a year of new demand from factories moving back to the U.S. Their answer is power built on site, from fuel cells, engines and turbines. Arcaro said developers now sign 15 to 20 year contracts for equipment once seen as a stopgap.
How Big Is 80 Gigawatts?
Big, against the grid we have. Demand across the lower 48 states set its record on July 29, 2025, at about 760 gigawatts, according to the Energy Information Administration’s hourly grid data. This summer’s high, on July 2, was 754 gigawatts. An 80 gigawatt gap is about 10.5% of that record. Run around the clock for a year, 80 gigawatts would use about 701 billion kilowatt-hours, roughly 17% of all the electricity sold to U.S. customers in 2025.
The number has moved fast. In a Feb. 27 article, Morgan Stanley put the shortfall at about 49 gigawatts by 2028, against 74 gigawatts of data center demand. Its May 13 outlook said nearly 50 gigawatts by 2028, up from about 15 gigawatts in 2025. The new figure runs a year further out, to 2029. Oaktree’s Howard Marks asked the same question on CNBC on Oct. 30: if the industry wants three to 10 times its current infrastructure, “where are they going to get three to ten times as much power?”
The Last Time Forecasters Expected a Boom
Big calls on power demand have a mixed record. In May 1999, Mark Mills argued in a report for the Greening Earth Society, summarized in Forbes, that the internet already used about 8% of U.S. electricity and that the digital economy would grow to use half of it within a decade. Jonathan Koomey and colleagues at Lawrence Berkeley National Laboratory found the internet estimate was too high by about a factor of eight.
The government’s own forecasts also ran hot. The Energy Information Administration’s 2005 outlook expected Americans to buy 5.22 trillion kilowatt-hours of electricity in 2025. They bought 4.06 trillion; the forecast was 29% too high. From 2005 to 2021, sales grew just 4.0% in total.


That changed after 2021. Sales rose 6.6% in four years, faster than in the 16 years before, and the first seven months of 2026 were up 1.3% from a year earlier. The agency’s October short-term outlook expects 2.3% growth this year and 1.6% in 2027.
U.S. power demand, as of Nov. 10, 2026
The Forecasts Missed in Both Directions
Scoring every outlook the agency published from 2005 to 2023 against 2025 shows a turn. Each edition from 2005 through 2015 projected more electricity sales in 2025 than happened. Each edition from 2016 on projected less. The 2023 outlook expected sales to slip about 0.3% a year from 2022; they grew 1.1% a year, leaving that forecast 4.2% short. The later outlooks came after a decade of flat sales and expected little growth, just before data centers, factories and electric cars began adding to demand. Turning points are where forecasts tend to fail: the Fed and private economists both missed the 2021 inflation surge by nearly four points.
The 2005 outlook saw power sales growing 1.8% a year through 2025. They grew 0.7%. Recent outlooks guessed too low
Average yearly growth in U.S. retail electricity sales from each Energy Information Administration outlook’s starting year to 2025: what the outlook projected (left) and what happened (right).
The agency’s newest long-term outlook, released April 8, expects sales of 4.25 trillion kilowatt-hours in 2029, 4.7% above 2025. That is growth of about 189 billion kilowatt-hours. Morgan Stanley’s shortfall alone, if those data centers ran all year, would be more than three times that. The two views are far apart, and the record shows that misses can run either way.
What to Watch
The test is whether the gap shows up in data or in deals. Watch monthly retail sales in the agency’s Electric Power Monthly. Watch whether next summer beats the 2025 peak. And watch who pays for the new lines and plants, the question behind Google’s claim that data centers built the right way can lower everyone’s bills. If the money behind AI slows, much of it coming from a small number of companies, the forecasts could be wrong again, this time on the high side.
Arcaro’s 80 gigawatt shortfall is about a tenth of the grid’s record peak, and Morgan Stanley’s estimate has grown with each update this year. The record argues for humility both ways: the government’s forecasts overshot by as much as 29% in the 2000s, then undershot once demand turned. The risk is that a number built on today’s spending plans meets the same fate as the internet power forecasts of 1999.